How Long Does It Take to Rewire a House? UK 2026 | C-Lec Electrical
Home Rewires • C-Lec Electrical

How Long Does It Take
to Rewire a House?

The honest range for a UK rewire is 3 to 15 working days depending on property size, access plus scope. This guide breaks it down by house type plus shows where the time actually goes from first fix through to certification.

Updated: April 2026
Standard: BS 7671 18th Ed Amend 3
Coverage: Bedford · Milton Keynes · Northampton
The short answer

A typical UK 3-bed semi rewire takes 5 to 10 working days. A 1-bed flat is usually 3 to 5 days. A 4-bed detached runs 7 to 14 days. A 5-bed period property with solid floors or hard plaster can stretch to 14 or 15 days. Add 1 to 2 days for full inspection plus testing on top of first fix plus second fix. Time is dominated by the first fix phase, not the second fix or certification.

By the numbers

The figures that matter

3to 5 days

1-bed flat

Compact layout, easier cable runs, single consumer unit area.

5to 10 days

3-bed semi

The UK average. Most rewires C-Lec quotes fall inside this window.

7to 14 days

4-bed detached

More circuits, more rooms, often two-storey loft cable runs.

1to 2 days

Test plus certify

Always extra to first fix plus second fix. Required for the EIC certificate.

Where to start

Four things to consider

First fix is longest

Lifting floors, chasing walls plus pulling cable accounts for 60% of the total job time.

Solid floors slow things

Concrete or screed floors mean surface trunking or chased channels. Add 2 to 3 days.

Hard plaster slows things

Pre-1960 lime or hard cement plaster takes longer to chase plus blunts disc cutters faster.

Test plus certify always extra

1 to 2 days for full BS 7671 18th Edition testing on top of fitting time.

The detailed answer

Where the time actually goes during a UK rewire

When clients ask how long a rewire takes, they are normally expecting a single number. The reality depends heavily on property size, access plus floor construction. A 1-bed flat with suspended timber floors plus easy loft access can be done in 3 working days. A 5-bed detached with solid concrete ground floors plus original lime plaster can take 14 or 15.

First fix dominates the schedule. Lifting floorboards, chasing channels into walls plus pulling new twin and earth cable from the consumer unit out to every socket, switch plus light position takes around 60 percent of the total job time. On a 3-bed semi this typically runs days 2 through 6.

Second fix is faster. With cables already in position, terminating sockets, switches plus light fittings then commissioning the new consumer unit usually only takes 2 to 3 days for a 3-bed.

Testing plus certification is mandatory plus always extra. Under BS 7671 18th Edition Amendment 3, every new installation needs full inspection plus test before the EIC certificate can be signed off. Allow a minimum of 1 day for a 3-bed plus 2 days for larger properties.

Other time variables that catch homeowners out:

  • Solid concrete floors. No floorboards to lift means surface trunking, chased channels or core drilling between rooms.
  • Hard plaster. Houses pre-1960 often have lime or hard cement plaster that chases slowly plus shatters disc cutter blades.
  • Listed status. Cable routes often have to avoid period features adding time plus complexity.
  • Decoration scope. If you want flush sockets in chased boxes rather than surface-mounted, that adds time.
UK regulation source check. BS 7671 18th Edition Amendment 3 (current standard, July 2024 publication, January 2025 enforcement) requires full inspection plus testing of every new installation before it can be energised plus certified. Part P of the Building Regulations requires a registered electrician or Building Control sign-off. C-Lec Electrical is NICEIC plus NAPIT registered plus serves Bedford, Milton Keynes, Northampton, Wellingborough plus Luton.
Cost breakdown

Real number ranges

Working days by property type

1-bed flat or compact 2-bed 3 to 5 days
3-bed semi or 3-bed terrace (the UK average) 5 to 10 days
4-bed detached or 5-bed period 10 to 15 days
Step by step

Inside a typical 3-bed rewire week

01
Day 1

Set-up

Carpets up, dust sheets down, furniture moved, power isolation plan agreed with the household.

02
Days 2 to 6

First fix

Cable runs pulled to every accessory, back boxes installed, consumer unit position prepped.

03
Days 7 to 9

Second fix

Sockets, switches plus light fittings terminated. New metal consumer unit installed plus commissioned.

04
Day 10

Test plus hand-back

Full BS 7671 inspection plus test, EIC certificate issued, Building Control notification submitted.

Practical guidance

Four ways to keep your rewire on schedule

Lock the spec on day one

Late changes to socket positions or kitchen layout add 1 to 2 days to the total schedule.

Clear access in advance

Lofts, cupboards plus understair spaces should be empty before the team arrives on day one.

Decide on smart kit early

Smart switches, dimmers plus underfloor heating each need their own back box plus cable spec.

Book the plasterer for week 2

Patch plastering should follow within 7 days. Any longer plus dust ingress becomes a problem.

Ready to talk?

Get a Free Rewire Quote

Free no-obligation site survey. Written itemised quote within 48 hours. NICEIC plus NAPIT registered. Six-year workmanship warranty across Bedford, Milton Keynes, Northampton, Wellingborough plus Luton.

Side by side

Compare the options

Easy access property

Easy access property

  • Suspended timber floors on both storeys allow fast cable runs.
  • Modern plasterboard walls chase quickly plus cleanly.
  • Loft fully boarded plus accessible for cross-floor runs.
  • Standard ceiling heights at 2.4m or thereabouts.
  • Schedule: normally hits the lower end of the 5 to 10 day range.
Difficult access property

Difficult access property

  • Solid concrete or screed ground floor requires surface trunking or core drilling.
  • Original lime or hard cement plaster slows wall chasing significantly.
  • Restricted loft access with hatches under 600mm or low headroom.
  • High ceilings or vaulted areas requiring scaffold or longer access platforms.
  • Schedule: add 2 to 5 days on top of the standard quote.

Timing is one part of the rewire decision. Cost plus disruption are the other two. Our home rewires hub brings all three into one place.

Part of the hub

Visit the Home Rewires Hub

This article is one chapter inside our complete Home Rewires knowledge base. The hub covers timing, cost, disruption plus regulation in a single index.

If you would like a fixed quote with a clear day-by-day schedule, our Bedford electrician page outlines our local rewire service plus how we book the testing day at the front of the job.

Frequently asked

How Long Does It Take to Rewire a House? FAQ

How long does a 3-bed rewire take in the UK?
5 to 10 working days for a typical 3-bed semi or terrace. The lower end is for easy access, suspended floors plus modern plaster. The upper end is for hard plaster, restricted loft or solid ground floors. Add 1 to 2 days for full BS 7671 inspection plus testing.
How long does a 1-bed flat rewire take?
3 to 5 working days for most 1-bed flats. Smaller floor area plus fewer circuits make this the fastest standard rewire scope. Block-of-flats access plus shared loft restrictions can push this slightly longer.
How long does a 4-bed or 5-bed rewire take?
7 to 14 working days for a 4-bed detached. 10 to 15 for a 5-bed period property. Larger floor area, more circuits plus often older plaster construction all extend the schedule. Solid floors add a further 2 to 3 days.
Does testing plus certification add time on top?
Yes. Full BS 7671 18th Edition Amendment 3 inspection plus testing is required before the EIC certificate is issued. Allow 1 day for a 3-bed plus 2 days for larger properties on top of first fix plus second fix.
Can a rewire be done faster if more electricians are on site?
Sometimes. Two electricians plus an apprentice can compress a 3-bed from 8 days to around 5 working days. Cost rises proportionally. Most homeowners prefer the standard pace because it allows daily check-ins plus reduces dust load each day.